Work progresses and with the drier, spring-like weather we’ve begun the excavation work essential for stopping the basement flooding as well for installation of water lines connecting the home & ADU to the well. Window installation & trim as well as repaired siding work has been completed on the home’s exterior. Next planned tasks are the removal of the large dead maples as well as the installation of the deck. It is a mystery as to why so many maples on the property are dead.
Excavation for the drainage perforated pipe which will connect to the dry well.
Power & water line excavations for the accessory dwelling unit.
New windows, new trim & new siding infill.
Interior electrical wiring nearly complete.
Huge dead maple, towering over the ADU, to be removed.